Construction Projects

 Building 2100- Nursing Renovation Project

nursing renovation project

• Board Approved ...................................................................................August 18, 2021
• Notice to Proceed...........................................................................September 20, 2021
• Architect Firm..................................................................................................Gensler
• Contractor...............................................................................George Mitchell Builders
• DSA Inspector...............................................................................Precision Inspections
• Project Management Firm.......................................................................................N/A


Information:
1. This project is approximately 60% completed
2. Contractor is waiting for DSA approval on new lighting fixtures to comply with Title 24. Approval is expected by the end of February.
3. This project is scheduled to be completed by the end of April 2022.


 

Disability Students Programs, and Services (DSPS) New Building Project

 
 dsps building  

•Board Approved ......................................March 17, 2021
•Notice to Proceed ....................................March 18, 2021
•Architect .................................................SGH Architects
•Contractor #1................................Silver Creek Industries
•Contractor #2.............................George Mitchell Builders
•DSA Inspector...................................Precision Inspections
•Project Management Firm.......................................... N/A


Punch List Items
1. Automated entrance door has been installed and is fully operational
2. Tile Veneer has been installed
3. Notice of Completion – Tentative – to be filed March 2022.
4. Grand Opening Event – March 2022


 Building 200, 300, and 800 Renovation Project

 building 200 300 800 renovation project

• Board Approved...........................................................................................September 21, 2021
• Notice to Proceed ............................................................................................October 18, 2021
• Architect Firm...............................................................................................Jimmy Sanders Inc.
• Contractor...........................................................................Erickson Hall Construction Company
• DSA Inspector.............................................................................................Precision Inspections
• Project Management Firm.....................................................................................................N/A

Pending Items:
This project thus far is on time and under budget. Building 200 is scheduled to be completed by August 30th, 2022.
The District is currently working with Parron Hall Furniture Distributors on the selection of furniture for building 200. A formal proposal for furniture will be placed in the April agenda.
Renovation of building 300 is scheduled to start in January 2023, and building 800 in May of the same year.
Thus far this project is running on time and on budget


 Building 700 - GYM HVAC Renovation Project

gym building

• Board Approved.........................................July 21, 2021
• Notice to Proceed...................................August 23, 2021
• Architect Firm.........................................SGH Architects
• Contractor....................................Vic's Air and Electrical
• DSA Inspector.................................Precision Inspections
• Project Management Firm.........................................N/A

Pending Items:
1. This project is scheduled to be substantially completed by the end of April 2022.
2. The District is waiting for the arrival of seven (7) Air Handler Units. ETA by end of February 2022.


Relocatable Classrooms (Interim Swing Space – completed)

   

 Building 700 - New Transformer Project

transformer project• Board Approved................................................................August 18, 2021
• Notice to Proceed........................................................September 13, 2021
• Engineer..............................................................Michael Wall Engineering
• Contractor ....................................................Chula Vista Electric Company
• DSA Inspector.............................................................Precision Inspections
• Project Management Firm.....................................................................N/A

Information:
1. This project is 85% complete and it's scheduled to be completed by the end of April 2022.
2. Imperial Irrigation District (IID) – the District has been waiting for the IID to come in and install their sector box and run their primary cables to the new meter panel. IID should complete this part of the project by the end of February 2022.


Building 3100 & 3200 Renovation (completed back in 2015/2016)

   